Project: ARA Antiesenhofen BA 06, Bl 01
Project description: Ausbau und Anpassung der ARA Antiesenhofen an den aktuellen Stand der Technik
Contractor: Gemeinde Antiesenhofen
Ortsplatz 1
4980 Antiesenhofen
Engineering office: HIPI Ziviltechniker GmbH
Salzburger Straße 23
4840 Vöcklabruck
Ansprechpartner: DI Walter Perathoner
Site manager: Fritz Jobst
Construction time: 04/2016- 06/2016
Purpose: Sewage disposal
Sewer maintenance/Pipe rehabilitation
Sewer maintenance/Building restoration
Method: Injection technique
Coating technique
Technology:
Combined construction   Cut-and-cover method 
100 m
Rehabilitation